The September 2026 Prime Building Cost Index puts building inflation at 5.1%, down from 9.7% a year ago, and prices rose 0.03% from August. Cement and steel got cheaper. Reinforcement and plumbing got costlier.
2 min read
Article tools
Listen to this article
Playback position
0:001:37
The Government Statistician, Dr Alhassan Iddrisu, has said that building costs in Ghana are rising at about half last year’s pace, yet plant and equipment costs jumped 19.1%.
He said building costs in Ghana were 5.1% higher in September 2026 than in September 2025. That is up from 4.6% in August, but about half the 9.7% recorded a year ago.
What this means is simple: building costs are still rising, but at a much slower pace than they were last year, he said.
Between August and September 2026, building costs rose by 0.03%. Put plainly, he said, a project costing GHC100,000 in August would cost about GH¢100,030 in September.
"The rise in the annual rate mostly reflects prices that fell in September 2025, not a fresh price jump this month," Dr Iddrisu said during a press conference in Accra on Tuesday October 27.
He further said that materials make up 76.5% of the building cost basket and account for 97.2% of headline inflation.
In September 2026, materials rose 6.5% and plant and equipment rose 19.1%. Labour fell 3.2%, which pulled the headline rate down he said.
Electrical works alone account for 41.1% of headline building inflation. Reinforcement rose 29.0% and plumbing rose 27.5%, while steel fell 8.8% and cement fell 6.1%.
"Finishing and installation inputs such as reinforcement and plumbing are pushing building costs up. Core structural inputs such as cement and steel are holding them down," he said.
Laud NarteyLaud Nartey is a current affairs editor with the MG News team at Media General, serving TV3 Ghana, 3News, Onua TV and more platforms.